This example has level resources of three resources for eight days. If the project is limited to two resources, how should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number. Show a. Paths would be 1,2,3,4 and 1,2,5 b. Path would be 1,2,3,4,5 c. Paths would be 1,2 and 3,4,5 d. Paths would be 1,2,3,5 and 1,2,4 Scheduled maintenance: Saturday, September 10 from 11PM to 12AM PDT
Home Subjects Solutions Create Log in Sign up Upgrade to remove ads Only ₩37,125/year
Chapter 6 terms and defnitions Terms in this set (7)as-late-as-possible (ALAP) schedule A schedule based on the latest start time of each activity in the project. as-soon-as-possible (ASAP) schedule A schedule based on the earliest start time of each activity in the project. resource constrained planning A network diagram and schedule that take into account the availability of a limited quantity of resources. resource leveling A method for developing a schedule that attempts to minimize the fluctuations in requirements for resources without extending the project schedule beyond its required completion time. Also referred to as resource smoothing. resource requirements plan A table that illustrates the expected utilization of resources by time period during the time span of the project. resource smoothing A method for developing a schedule that attempts to minimize the fluctuations in requirements for resources without extending the project schedule beyond its required completion time. Also referred to as resource leveling. resource-limited scheduling A method for developing the shortest schedule when the quantity of available resources is fixed. This method will extend the project completion time, if necessary, in order to keep within the resource limits. Sets with similar termsSuccessful Project Management: Chapter 613 terms brice_bader ISOM 300 - Ch. 622 terms ntkinghorn BA 421 Resources Lesson 515 terms paula_razzaq Project Management Ch. 828 terms gamlirefur Sets found in the same folderIntro to Project Management Chapter 125 terms cwoodley Project Management Ch. 220 terms czubad Project Management Ch. 317 terms czubad Other sets by this creatorBusiness English Terminology19 terms czubad Computing Fundamentals37 terms czubad Matching5 terms czubad IC3 GS5 Computing Fundamentals Glossary29 terms czubad Other Quizlet setsSupply Chain Exam 2 Chapter 650 terms kierstenlenherr Ops Final73 terms jkrause94 MGMT exam #288 terms hyg5048 Finals Topics/Ques - Planning (cont.)39 terms michellefrances Related questionsQUESTION What would be an example of an upscale casual restaurant ? 15 answers QUESTION Which financial statement would a potential investor primarily use to assess the company's liquidity and financial flexibility? 2 answers QUESTION When providing treatment to a patient while he or she is being rescued, it is MOST important to: 15 answers QUESTION What are the functions of foot-ankle assemblies ? 9 answers Is a method for developing the shortest schedule when the quantity of available resources is select?Resource-limited scheduling is a method for developing the shortest schedule when the quantity of available resources is fixed and may extend the project completion time in order to keep within the resource limits.
Is a method for developing a schedule that attempts to minimize the fluctuations in requirements for resources?Resource leveling, or smoothing, is a method for developing a schedule that attempts to minimize the fluctuations in requirements for resources. This method levels the resources so that they are applied as uniformly as possible without extending the project schedule beyond the required completion time.
What is resourceThe resource-limited schedule is a project schedule whose schedule activities start dates, and finish datesdirectly reflect the availability of all resources in question. Typically, a resource-limited schedule will not have any start dates that are early or late.
What is the difference between resource smoothing and resource leveling?Resource smoothing is used when the time constraint takes priority. The objective is to complete the work by the required date while avoiding peaks and troughs of resource demand. Resource levelling is used when limits on the availability of resources are paramount.
|