Is a time by which an activity may be delayed without affecting any subsequent activity *?

← Prev Question Next Question →

0 votes

165 views

asked Feb 23 in General by Kartikruhil (41.6k points)
closed Feb 24 by Kartikruhil

A float (or slack) in a critical path method (CPM) is amount of time that a task can be delayed without causing any delay to
1. Subsequent tasks and project completion date
2. Interdependent tasks
3. Subsequent tasks only
4. Preceding tasks
5. Project completion date only

  • construction-materials-and-management
  • project-planning

Share It On

1 Answer

0 votes

answered Feb 23 by Neeljain (30.0k points)
selected Feb 23 by Kartikruhil

Best answer

Correct Answer - Option 1 : Subsequent tasks and project completion date

Explanation:

Float

  • It is associated with activity times.
  • It is analogous to the slack of events in PERT.
  • It is the range with which start or finish activity may fluctuate without affecting the project completion time.
  • Floats are of following types:
    • Total float: The time span by which starting or finishing of an activity can be delayed without delaying the completion of the project. It is the maximum available time over the activity completion time.
    • Free float: The delay which can be made without delaying succeeding activities. It affects only preceding activities.
    • Independent float: It is the minimum excess available time that exists without affecting any of the succeeding or preceding activities.
    • Interfering float: It is similar to head event slack.

So, 

A float (or slack) in a critical path method (CPM) is the amount of time that a task can be delayed without causing any delay to Subsequent tasks and project completion date.

← Prev Question Next Question →

Find MCQs & Mock Test

  1. Free JEE Main Mock Test
  2. Free NEET Mock Test
  3. Class 12 Chapterwise MCQ Test
  4. Class 11 Chapterwise Practice Test
  5. Class 10 Chapterwise MCQ Test
  6. Class 9 Chapterwise MCQ Test
  7. Class 8 Chapterwise MCQ Test
  8. Class 7 Chapterwise MCQ Test

0 votes

1 answer

Statement (I): Critical path(s) through a CPM network can be identified even without working out the backward pass computations by a competent user. S

asked Feb 24 in General by SiddharthShete (35.4k points)

  • construction-materials-and-management
  • project-planning

0 votes

1 answer

Independent float is an amount of time by which the start of an activity may be delayed without affecting 1. the preceding or the following activity 2

asked Feb 24 in General by SiddharthShete (35.4k points)

  • construction-materials-and-management
  • project-planning

0 votes

1 answer

Consider the following statement associated with critical path: 1. Critical path is the most important sequence of activities which has no float and w

asked Feb 24 in General by SiddharthShete (35.4k points)

  • construction-materials-and-management
  • project-planning

0 votes

1 answer

Slack time in PERT analysis

asked Mar 1 in General by ZebaParween (30.0k points)

  • construction-materials-and-management
  • project-planning

0 votes

1 answer

Free float is mainly used to

asked Feb 21 in General by BabulPandey (59.9k points)

  • construction-materials-and-management
  • project-planning

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

Categories

  • All categories
  • JEE (28.1k)
  • NEET (8.5k)
  • Science (740k)
  • Mathematics (240k)
  • Statistics (2.8k)
  • Environmental Science (3.6k)
  • Biotechnology (536)
  • Social Science (102k)
  • Commerce (62.1k)
  • Electronics (3.7k)
  • Computer (15.6k)
  • Artificial Intelligence (AI) (1.4k)
  • Information Technology (13.2k)
  • Programming (8.6k)
  • Political Science (6.4k)
  • Home Science (4.0k)
  • Psychology (3.3k)
  • Sociology (5.5k)
  • English (57.3k)
  • Hindi (20.3k)
  • Aptitude (23.7k)
  • Reasoning (14.6k)
  • GK (25.7k)
  • Olympiad (527)
  • Skill Tips (72)
  • CBSE (710)
  • RBSE (49.1k)
  • General (56.9k)
  • MSBSHSE (1.8k)
  • Tamilnadu Board (59.3k)
  • Kerala Board (24.5k)

...

Is the amount of time by which an activity may be delayed without causing any delay to subsequent activity?

In project management, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to: subsequent tasks ("free float")

What does slack time refer to?

Slack time is often defined as the amount of time you can delay the task without interfering with another task or affecting the completion date of your project. As we mentioned earlier, this happens when flow becomes unbalanced. Usually, imbalance occurs when some team members finish tasks before the rest of the team.