When you're trying to estimate the time between the beginning and the end of any project, the critical path follows the longest route. The standard deviation, on the other hand, uses the the most optimistic and most pessimistic estimates to calculate the most likely -- if not the most conservative -- time for the completion of a project.
Why the Critical Path Is Longest
The critical path represents how long it takes to complete a project, based on the completion of the each of the activities necessary for completion. It's the total time for the completion of every step -- whether it's done in house or by a supplier or contractor -- that must be finished in order to call the project fully finished. Unlike the standard deviation in a project, it doesn't rely on a comparison of the best- and worst-case scenarios.
The Standard Deviation
The critical path isn't the shortest route in the standard deviation; the standard deviation is the amount of variation from the average time for completion of any one of the elements of a project. It's used to calculate the most likely time for completion of any element in the critical path, or -- if you add up the most likely completion times, it's the total time for completion of the project. The standard deviation looks very pessimistic at first. You subtract the completion time required for the (always smaller) best-case scenario from the always-larger time required by the worst-case scenario. You then divide the result by six to determine the standard deviation.
Standard Deviation for the Whole Project
If your project involves five activities, calculating the standard deviation for each activity tells you the most likely time for its completion. If the most pessimistic estimate for the first element is 11 weeks from start to completion and the most optimistic estimate is two weeks, subtract 2, the most optimistic estimate, from 11, the most pessimistic. Repeat the process for each activity or element.
What the Critical Path and Standard Deviation Represent
The standard deviation for each project element represents the most likely completion time for that part of the project. When you've subtracted the most-optimistic estimate from the most-pessimistic estimate for each part of the project, add the result of each together and divide by six. The result is the standard deviation -- and the most likely number of days, weeks or hours needed for the overall project's completion.
The Language of Composition: Reading, Writing, Rhetoric
2nd EditionLawrence Scanlon, Renee H. Shea, Robin Dissin Aufses
661 solutions
Technical Writing for Success
3rd EditionDarlene Smith-Worthington, Sue Jefferson
468 solutions
Technical Writing for Success
3rd EditionDarlene Smith-Worthington, Sue Jefferson
468 solutions
Technical Writing for Success
3rd EditionDarlene Smith-Worthington, Sue Jefferson
468 solutions
After reading this article you will learn about the calculation of standard deviation of the project.
In PERT, the three time estimates are used to find the expected time to complete an activity and, then, by the process of standard deviation and variance, we find the probability of the total estimated project duration of completing all the activities and, thus, the project. PERT follows the beta-distribution curve to work out the standard deviation, which is one- sixth of the range.
The steps taken to calculate standard deviation of the total project duration are to:
(a) Find the critical path with time estimates and then identify the activities on the critical path.
(b) Standard deviation per activity (symbol used St):
St = tp-to/6
(which is one-sixth of the range of time estimated and the range of time estimate is the difference between Optimistic and Pessimistic time estimates).
(c) Calculate the variance per activity symbol used as Vt and Vt = St2 = (tp-to/6)2
(d) Find the standard deviation of the project total duration as S.D. = √Sum of all V’t (representing the total te-s for all events on the critical path).
Illustration 1 (about Probability in PERT):
Before we proceed further, we can start working, following the same illustration as per table below, and using the above formulae:
CP represents activity on critical path:
1. Project duration expected E = 5 + 15 + 4 + 5 = 29 days (i.e. the total of te-s for activities on the Critical Path).
2. Variance of the Critical Path = 2.79 + 2.79 + 0.45 + 0 = 6.03
3. Standard Deviation (SD) of project duration is √6.03 = 2.46.
We have seen earlier that t has the probability of 0-5 and this probability is applicable even on a cumulative situation till we reach the end event. This is valid even when we accumulate the te-s of all preceding events and can still say the probability as 0.5 for the cumulative time as on that event. When we say the project duration expected as TE we consider TE as the mean of the distribution with probability of 0-5.
From the above calculated details, PERT suggests to work out the deviations from the mean of the distribution in units of standard deviation and read the probability from the normal distribution table.
When we would like to find the probability of a target scheduled date Ts, PERT works out the TE and SD as explained already and then finds out how much Ts is deviated from the mean distribution (TE) in units of standard deviation (SD). We have already worked out Ts and SD of the illustrated projected detailed on the table.
Following the PERT we can answer questions like:
(a) What is the probability of completing the project by (1) 29 days, (2) 32 days, (3) 27 days?
(b) In how many days the project can be completed with a probability of 95%?
Steps to be taken are:
Step 1.
Calculate the expected time t per activity following the formula te=to+4tm+tp/6
With the te as calculated, draw the network and find the critical path and the expected project duration, TE .
Step 2.
Calculate (a) the standard deviation per activity representing one-sixth of the range of the estimated time i.e. St= tp– to/6 and then
(b) Variance per critical activity i.e. St2 = (tp– to/6)2
(c) and the standard deviation of the project, SD, the square root of the total of the variances of all critical activities : SD = √Sum of St2 of Critical activities. (SD = 2.46 in the illustration above).
Step 3;
Calculate the deviation of the scheduled date Ts from the mean of the distribution, i.e. the TE in units of S.D. The value of such deviation is Z and the formula to calculate is, Z = TS-TE /SD.
Step 4:
From the value of Z and consulting the normal distribution table (partly quoted in the later part of this chapter in 6.1.03) we find another, value which we are to adjust with 0-5 (the mean of the distribution) and find the probability of Ts.
Step 5:
The adjustment with 0-5 depends upon the length of time for Ts and for Te. Obviously, when Ts > TE the probability is more than 0-5; therefore, we add the value read out from the normal distribution table and when TE > Ts we are to deduct from 0-5.
Answer to questions:
1. a-1) What is the probability of completing the project by 29 days when Ts is 29 days?
Z = TS-TE /SD = 29-29/2.46= 0 the value from the normal distribution table for 0 is zero.
Therefore, the probability of completing the project by 29 days = 0.5 + 0 = 0.5 i.e. 50%.
2. a-2) When Ts is 32 days
Z = TS-TE /SD = 32-29/2.46= 1.22; the value from the normal distribution table for 1.22 is 0.39.
Ts is more than TE, therefore, the probability is 0-50 + 0-39 = 0-89 or 89% (or the probability of not meeting the date is 100 – 89 = 11%)
3. a-3) When Ts is 27 days
Z = TS-TE /SD = 27-29/2.46= – 0.81; the value against 0.81 from the normal distribution table 0.29. T5 is less than TE, therefore, the probability is 0-50 – 0-29 = -21 or 21%.
(b) In how many days the project can be completed with the probability of 95% (or with 95% confidence level)?
We presume Ts is the unknown number of days and, as the probability is more than 0-50 (i.e. more than 50%), Ts must be more than TE (in number of days) and the value per table is 0.95 – 0.50 = 0.45. We also note from the table that we can get 0-45 when the value of Z is 1.65 (0.4505).
Ts – 29
Now we find the equation Z = TS-29 /2.46 = 1.65
or, Ts = 29 + 2.46 x 1.65 = 33 days.
We can say with 95% confidence that the project will be completed in 33 days.
Illustration 2 on Probability as per PERT:
Following is a table of activities of a project with estimated optimistic, most likely and pessimistic duration (in days):
From the details as per above table we are to:
(a) Draw the project network;
(b) find the critical path;
(c) Calculate the variance of the critical path;
(d) Find the probability of completing the project (following the critical path) in 41 days.
Step 1: Calculate the estimated time t per activity as per PERT:
Network construction with te-s and the critical path.
Answer to questions (c) and (b).
Legend (Network):
Legends (2) The critical path shown with double-line arrows joining the events showing EST = LFT.
(3) The Critical Path represents activities A, C, G and I.
(4) Project duration, TE is 36 days.
Step 2. Calculations of the
(a) Standard deviation of the activities duration, St =tp-to/6 ;
(b) Variance of the activities S,2 on the Critical Path; Total of variances of Critical Path = 25.
Answer to question (c).
Standard deviation of the project duration (make image)
SD = √Total Variance of all critical activities
= √25
= 5
Step 3:
Deviation of the schedule date, Ts (which is given as 41 days) in units of SD is Z and
Z = TS-TE/SD
Or
Z=41-36/5=1
Step 4:
The normal distribution table shows the value for 1 as 0-3413. We know TE of 36 days as probability 0.5., Ts of 41 days being greater than TE, we are to add 0.3413 with 0.5 and find probability of 41 days as 0.50 + 0.34 = 0.84 or 84%.
Illustration 3: (on Probability as per PERT):
Following is a table of activities of a project with estimated optimistic, most likely and pessimistic duration in weeks:
Considering the above details, we are to:
(a) Draw project network;
(b) Identify the critical path on the network;
(c) Find the probability of completing the project in 32 weeks;
(d) Find the estimated weeks of completion with a probability of 90%.
Step 1:
To Calculate the Estimated time te per activity as per PERT:
... Standard Deviation SD = √6.83 = 2.61
With the above te -s and the activities with the precedent relationship of events we would like to prepare the network construction and then we find:
1. ESTs of the events, starting with event (1) as zero EST, then following the forward pass rule considering the longest EST when two or more activities converge to one event, till we reach to the last event.
2. LFTs of the events, starting with the last event, the last events LFT being the same as its EST. Then follow the ‘backward pass’ and find the LFT of the tail event (as LFT of head event, less tij) and, considering the shortest time units, when two or more activities emanate from one event.
Solution to question (a) and (b) drawing the project network and find the critical path:
Recapitulation of Time elements in network construction:
(1) EST for event 4: activities C, E and H converge with C for 0 + 9 = 9 weeks, E for 7 + 9 = 16 weeks and H for 8 + 7 = 15 weeks. Therefore, we take the highest, i.e. 16.
(2) LFT for event 2: activities E and F emanate from it coming backward from event 4, the LFT for 2 is 16 – 9 = 7 and, from event 6, the LFT for 2 is 23.5 – 5 = 18.5. Therefore, we take the lowest, i.e. 7.
We find the events 1, 2, 4, 5, 6 and 7 are having EST = LFT and, as such, they are critical events and the double-line arrows shown in the network represent Critical Path with activities A, E, I, J and L; total project time being 28 weeks, i.e. TE is 28 weeks.
Solution to question (c) to find the probability of completing the project in 32 weeks.
Step 2:
Calculations of duration:
(a) Standard deviation of the activities duration St = tp-to /6 on critical path marked CP.
(b) Total of variances on Critical Path = 6-83
(c) Standard Deviation of the Project Duration, = √6-83 = 2.61
Step 3:
Deviation of the scheduled date Ts (which is 32 weeks in question), in units of SD is Z and the value of:
Z= TS-TE/SD = 32 – 28/2.61 = 1.53
Value of 1-53 per normal distribution table = 0-4370 = 0-44 (approx.).
Step 4:
We are to add 0-44 with 0-5; since 32 days is more than the mean project duration of 28 weeks, we are to add i.e. 0.50 + 0.44 = 0.94.
... The probability to complete the project by 32 days is 94%.
Solution to question (d):
Find the project duration with 90% probability. Ts is the unknown project schedule, it is more than TE as the probability 90% is more than the probability of 50%. The value to adjust with 0.50 is 0.90 – 0.50 = 0.40. From the normal distribution table we find the corresponding value of 0.40 is 1.28. In other words, the value of Z is 1.28.
Therefore, putting the known values Z = TS-TE/SD =TS-28/2.61 = 1.28.
or , Ts = 28 + 2.61 x 1.28
= 28 + 3.34
= 31.34 weeks.
We can say with 90% confidence level that the project can be completed by 31-34 weeks.
Summary Note:
We find that the techniques followed in CPM and in PERT are almost same to start with except that:
1. PERT suggests an wider range of estimation of the activity duration ranging from optimism to pessimism; and
2. PERT extends to find out the probability (following the statistical theory) of the worked out project duration.
It is worthwhile to mention here that, considering too many assumptions of the time estimates, errors in such assumptions may accumulate in a compounding process, which, noted by management expert, may even reach to about 33 per cent.